248 S Hale - Exterior, Garage, & Base

248 S Hale - Oak Floors Installed

The floors & stairs are in.  Sidewalk, front, & rear stoop are poured. Interior doors, trim, and base are being installed. 

111 S Bothwell

Here is a rough front elevation for the spec house on Bothwell.   Construction begins soon. 

248 S Hale - After Insulation

We just passed the insulation inspection.  The Brick & Siding Are just about done.  Getting ready for drywall.