We just finished demolition of the old house on the property. We will be moving right into excavation for the new home foundation. This is a great neighborhood in Elmhurst with lots of new single family homes being built.
106 W Aldridge — Finished
106 W Aldridge Ave, Palatine is finished and ready for move-in.
106 W Aldridge Progress
We are just about to start the carpenter trim & doors. Tile and wood floors are going in now. Oak stairs have been installed. Everything is moving along and we should be complete by the end of the summer.
Project Progress
134 W Aldridge is finished. Final professional photos are coming. But I took a few regardless.
At 106 W Aldridge, We are now installing rough electric.
November
The carpenters have just started laying out the roof at 106 W Aldridge. And 134 W Aldridge has had the driveway paved and the site graded.
106 W Aldridge — Framing
Foundation is backfilled, underground plumbing is in, and we started the rough framing.
106 W Aldridge
We have excavated and are now pouring the footings for the new home at 106 W Aldridge in Palatine.
2300 Brockway — Completed Home Photos
2300 Brockway is finished. Here are some photos.
August Home Progress
156 has been completed, but we weren’t able to take interior finished photos.
134 just had the oak stairs installed at the 1st floor & basement.
2300 is just about done. Still finshing up a few last things and touchups. Here are a few interior photos of the progress.
134 W Aldridge July Progress
On the exterior we are starting the siding. On the interior, insulation has been installed and we will be starting drywall.