Here are some shots of 1850 Hamilton just before and after the foundation forms were put up. We just passed the inspection today and the walls will be poured tomorrow. Now that the weather is cooperating we should really be able to get moving on this home.
Hickory - Trusses
Here are a few shots just before and after the crane put up the trusses.
22 W Summerset Ct. - Final
Summerset is finished. Here are the photos.
Hickory - Second Floor Framing
The cold weather continues to slow us up. We are just starting the second floor walls for Hickory. I can already tell this house is going to look good. The layout is going to work really well.
Hickory - Steel & Deck
We got the first floor deck on just before the temperatures dipped. It may be too cold to work for the next few days.
Summerset - Exterior
The exterior is looking nice. There are still touch ups and cleaning to do, but for the most part the exterior is finished.
Hickory - Backfill, Sewer & Water
The next step will be to set the steel and then we can start the deck & framing.
Hickory - Footings
The footings have been poured and protected for the cold. We will have to wait for a warmer day to continue with the foundation walls.
Summerset - Progress
All the masonry work has been completed. It's been a slow process due to the cold weather. On the interior we are just getting ready to set oak floors.
901 N Hickory - Demolition & Excavation
901 N Hickory in Arlington Heights had a small old house that was in very bad condition. We put together a nice plan for a great looking new home on this lot. Everything was approved so now we are finally underway. Here are some shots of the demolition.