1017 North Beverly Lane, Arlington Heights
Finished Home Photos.
Here are a few photos of the finished home.
Slow going with the winter weather, but here is where we are at with the rough framing. There’s still work to do, but were just about to start the pluming & mechanicals.
We are done with the rough. After the Village inspections we will start masonry & siding on the exterior and insulation & drywall on the interior.
Here are some final interior photos.
We are waiting on pouring the basement concrete before we can continue on this one. Weather has been too cold the past few weeks.
Here are a few progress photos of this project. We are getting there...
We got slowed down a bit with the cold weather around the holidays, but things are moving again. Just about to start the shingles. Once ComEd hooks up the electric we can pour the basement concrete.