We purchased a large piece of property in Palatine with an old house to be torn down. The property has been subdivided for us to build 3 new homes. Before demolition we let the local fire departments use the old home for practice.
649 S Oak - Final
947 N Haddow - Siding
Siding is being installed. And inside drywall is just finishing up.
649 S Oak - Cabinets & Sidewalks
Inside we installed the cabinets & other carpenter trim. Outside we rough graded and installed the sidewalks.
947 N Haddow
Rough plumbing is finished and we’re starting the hvac and fireplace install.
649 S Oak - Siding & Drywall
Siding is being finished and on the interior the drywall was just hung.
5N773 Rochefort - Final
Had a professional take some photos.
5N773 Rochefort - Final Photos
947 N Haddow - Framing & Trusses
The rough framing and roof trusses are finished. Next up is to install the windows.
5N773 Rochefort - Grading
Here we have the final rough grades, but we still need the top soil, landscaping, and driveway asphalt.