106 W Aldridge Ave, Palatine is finished and ready for move-in.
106 W Aldridge — Finished
106 W Aldridge Ave, Palatine is finished and ready for move-in.
106 W Aldridge
106 W Aldridge Ave, Palatine is finished and ready for move-in.
We are just about to start the carpenter trim & doors. Tile and wood floors are going in now. Oak stairs have been installed. Everything is moving along and we should be complete by the end of the summer.
134 W Aldridge is finished. Final professional photos are coming. But I took a few regardless.
At 106 W Aldridge, We are now installing rough electric.
The carpenters have just started laying out the roof at 106 W Aldridge. And 134 W Aldridge has had the driveway paved and the site graded.
Foundation is backfilled, underground plumbing is in, and we started the rough framing.
We have excavated and are now pouring the footings for the new home at 106 W Aldridge in Palatine.